Page 13 - 00 Volume 5 The Mine
P. 13

The workings were safely carried on, and during    the main shaft, when trees and branches in the drift
     the year confined to headings and bords, no pillars      caused great delay. Provision was made to put on great
     being taken out. The ventilation is fairly good, although   pressure to force down the cylinders, which were in
     at times a change of wind causes a stagnation, which     segments and built in the top, while the sand and drift
     soon disappears.                                         were removed by a dredging-machine.
           The books are well kept, and the Act complied            No water was pumped from the shaft until the
     with. A copy of the plan of the workings of the mine     coal had been reached, when a Tangye pump was used
     has been sent to me, as required by the Act. The         to keep the shaft dry whilst the coal was sunk through
     number of men employed is eight on the surface and on    and the shaft bricked-up. Connection was made with
     steamer and punts, and nineteen below ground: total,     the heading-drive from the main shaft on the day

     twenty-seven. The output for the year was 4,839 tons.    previous to my visit on the 11th December last. The
                                                              depth of the second shaft is 204ft., the coal being 24ft.

                                                              in thickness, and as the main shaft is only 174ft. in
     Ralph's Taupiri Mine.                                    depth the pumping will be from the deepest one.
                                                                    The ventilation of the mine is good, the fan being
            (8th July) Only two men employed, at pillar-      still used: 9,070 cubic feet of air per minute was
     work near the out-crop. General and special rules hung,
     the latter without the required names. I requested Mr.   passing through the working places at the time of my
     Ralph to see to this. Shaft unfenced. This was attended   last visit for the use of fifty men and one horse below
                                                              ground.
     to at once.                                                    From the 20th September until the second
           The workings in this mine during the year have       opening was made the mine was worked in shifts in
     been: driving the new dip, removing a pillar in the old   order that not more than ten men were taken below at
     mine which was under the place where the hauling-
     engine formerly stood, and sinking a shaft. It was found   one time.
     that, on account of the quantity of water in the new dip,      The report-books are well kept, and the
     it would be more economical to work the mine by          provisions of the Act complied with. A copy of the plan
     sinking a shaft on the land between the railway and the   of the workings of the mine has been sent to me as
     Waikato River; the dip was therefore abandoned, and      required by the Act.
     the timber drawn. The shaft was then sunk to a depth of        The number of men employed was sixteen on the
     160ft., and through a seam of coal 65ft. in thickness.   surface and fifty below ground: total sixty-six. The
           The cover over the coal was of such a nature that   output for the year was 29,460 tons.
     no difficulty was experienced in sinking, as the running   Taupiri Reserve Mine.
     drift, found elsewhere in the neighbourhood, did not
     exist in the shaft. A bore-hole was made near by, and a        The workings in this mine for the year have been
     working shaft about 10ft. by 6ft. is to be sunk with as   under the Lake Kimihia. A series of bore-holes have
     little delay as possible. The first shaft will be used as a   been made, showing the depth of the cover, which is
                                                              from 48ft. to 77ft. in thickness, chiefly strong fireclay.
     pumping and upcast shaft.                                The bords are worked 14ft. in width, and the pillars are
           At my visit to the mine on the 10th December, I    21ft. in thickness. The height of coal worked is 13ft.,
     found that no cages were used, and that men were
     raised and lowered by the engines without being          and not less than ft. of coal left for a roof. It may
     securely stayed to the rope, as provided in section 25 of   therefore be considered that there is no special danger
                                                              in working under the lake so long as the thickness of
     the general rules. I instructed the manager to see that
     this precaution was taken in future, and to make the     the cover mentioned continues and the pillars are not
     entries in the report-book in a more systematic manner.   interfered with.
                                                                    Thirty-seven men are employed at the mine,
           The provisions of the Act were otherwise fairly      seven on the surface and thirty below ground. The
     well complied with. The average number of men
     employed was six on the surface, including manager       ventilation was good; 4,408 cubic feet of air per minute
     and engineers, and ten men below ground: total,          passes through the workings, giving 116 cubic feet per
                                                              minute for thirty-seven men and one horse working in
     sixteen. The total output for the year was 2,079 tons.
                                                              the mine.
                                                                    The report-book is well kept, and a copy of the
     Taupiri Extended Mine.                                   plan of the workings of the mine has been sent to me as
           The workings in this mine during the year were     required by section 45, and the other provisions of the
     driving headings and opening fresh bords to the          Act complied with. The output for the year was 17,221
     southward, driving a heading to the northward to         tons.
     connect with the second shaft, which was sunk about 10         No very serious accidents occurred during the
     chains from the main working-shaft. The second shaft,    year. The list of accidents reported are as
     which is 10ft. in diameter, sheathed with cast-iron      follows:-
     cylinders, was sunk with considerable difficulty on
     account of the sandy drift and quantity of water to be         - Benjamin Housley got accidentally struck by a
     contended with.                                                     pick on 18th January, in the Taupiri
           Bore-holes had been made in a circle from the                 Reserve Mine.
     surface down to the coal, and it was found that no             - William Patterson was injured by a rail
     obstacles were in the way, as was the case in sinking               bouncing up and striking him on the foot on
   8   9   10   11   12   13   14   15   16   17   18