Page 36 - 00 Volume 5 The Mine
P. 36

Bucyrus Erie, later to be nicknamed the 120-B.
                                                                     During this stage of the operation the 120-B
                                                               was  used  as  a  drag-line.  Later  the  boom  was
                                                               removed and a shovel unit attached.
                                                              A  coal  train  serviced  the  bins  twice  a  day  out
                                                              ofHuntly. Large quantities of coal were being mined
                                                              by a staff of only 17 men, far fewer than required by
                                                              an underground system.
                                                                    The mine constructed a boring plant which
                                                               was erected on a barge and testing was conducted on
                                                               areas  in  the  south-western  section  of  the  lake  to
                                                               quantify the  amount and  quality  of  coal  under  that
                                                               section of water.
                                                                    The hard fireclay in the exposed pit was taken
                                                               and  dumped  beyond  the  stop-bank,  forcing  the
                                                               once-large lake to retreat to the north and now it is
                                                               only a shadow of its former self.
     The original Perry’s farmhouse was converted for use           Drainage from the hills to the south of the lake
     as  an  office  by  the  mining  contractor  Downer  &    was  through  a  canal  that  was  dug  parallel  to  the
     Company.                                                  railway  line  as  the  water  could  not  now  find  the
                                                               lake it once did.
                                                                    Once  the  thick  sub-bituminous  seam  was
                                                               revealed the coal was blasted and taken out of the
            In  1943  Bill  Scurr,  one  of  the  miners,      ever-growing put via a conveyor belt that could be
       suggested that the level of Lake Kimihia be lowered     lengthened or shortened according to the location
       to increase production from the mine. Later he had      of  the  coal  face.  The  many  galleries  of  the
       the  satisfaction  of  seeing  the  Lake  and  the  Mine   underground workings were exposed.

       developed according to his ideas.                            The  coal  went  through  a  crushing  plant  in
            In  1944  the  New  Zealand  State  Coal  Mines
       took  over  and,  after  inspection,  decided  to  close
       the  underground  workings  and  use  opencast
       methods.  Downer  &  Co.  were  contracted  to  work
       the mine.
            Coal bins (hoppers) were built on the side of
       the hill with the railway line running under them for
       easy  loading  of  carriages.  At  this  early  stage  the
       coal was recovered from the pit area and brought
       to  the  bins  by  means  of  a  'flying  fox'  pulley
       system. A tall tower, placed above and behind the

       bins, supported the flying fox.
            The  control  house  for  the  unit  was  just
       above  the  bins.  The  'fox  worked  on  a  grab
       method similar to the dragline style of the 120-B.
            The company built a row of seven houses just
       above  the  last  railway  cutting  before  the  bins  and
       provided  a  good  third  to  half  of  an  acre  for  each
       house.  This  allowed  for  large  back  lawns  and
       gardens.
            Initially two areas in the hills were worked and
       Athey  Wagons  and  'carry-alls'  were  used  to         120-B in its latter stage of construction & testing.
       remove the overburden. It was decided to drain an            Assembly  instructions  for  this  imported
       area  in  the  South­eastern section of the lake  and a   machine were all in Russian making its construction a
       stop-bank (coffer dam) was  built by the 'carry-alls'   hit-or-miss  method  for  the  most  part.  When
                                                              completed,  the  testing  of  the  machine  was  even
       using filling from the hills.                          more harrowing through discovering what each lever
            On completion of the stop-bank the enclosed       and control did when operated!
       area  was  drained  by  large  pumps  and  stripping         Harry  MacDonald  (crouched  6th  from  left)
       commenced  through  the  use  of  wagons  drawn  by      became  admired  for  his  skill  at  operating  the
       tractors.  These  wagons  were  loaded  by  a  large   machine. He had previously operated the Flying Fox
       electrically  driven  excavator  called  the  120      over the first opencast pit.
   31   32   33   34   35   36   37   38   39   40   41